ACM |
Quantity |
Location |
|
|---|---|---|---|
| TJA – Mudded Fittings on F/G Lines | |||
| TJB – Mudded Fittings on Foam Lines | |||
| TJC- Mudded Fittings on Tar Paper Lines | |||
| TTA – Hot Water Tank Insulation | |||
| TPA – Mag Block Pipe Cover | |||
| TPC – Tar Paper Pipe Cover | |||
| MFA – 9 x 9 Floor tile and mastic | |||
| MFB – 12 x 12 Floor Tile and mastic | |||
| MLA – Paper Backing on Lights | |||
| Z – Terrazo Not Sampled | |||
ABATEMENT HISTORY |
|||
DATE |
MATERIAL REMOVED |
AMOUNT |
ROOM OR LOCATION |
10/00 |
TJA, TJB, TPA and TTA |
ABATEMENT |
ME ROOM 1 |
12/01 |
MFA and Mastic |
ABATEMENT |
ROOMS 108,113 AND 115 |
08/02 |
MFA and Mastic |
ABATEMENT |
ROOMS 201C and 201 I |
05/05 |
MFA and Mastic |
1200 SF |
Third Floor Hallway |
06/05 |
MFA and Mastic |
1200 SF |
Second Floor Hallway |
05/06 |
TJC |
20LF |
Kilin Room 102 |