skip the i-GuideIllinois State UniversityAdmissions at ISUAcademics at ISUEvents at ISUMap of ISUISU A to Z ListingISU AccessibilityISU 150th Anniversary
Environmental Health and Safety

For more information

Main ACM Locations

Asbestos Containing Material
Walker Hall BLD #305

ACM
Quantity
Location
MMJ - Old Vinyl Cove Base   Rooms and Hallways
MTA - Transite Shingles  (Assumed)   Roofing
Z - Terrazo Has not been sampled   Entry ways
TPA - Layered Paper Pipe Cover   ME Rooms and Pipe Chases
TPB- Mag Block Pipe Insulation   ME Rooms and Pipe Chases
TJA – Mudded Fittings on F/G Piping   ME Rooms and Pipe Chases
TTA – Tank Insulation   Removed From ME Room, in June of 04.
MFA – 9 X 9 Floor Tile and mastic  
39,877 SF
Rooms, Hallways and Spaces Throughout 1st - 4th Floors
MFB – 12 X 12 Floor Tile and mastic  (Old) 
8,377 SF
Rooms and Spaces 1st Through 4th Floor; 181, 182, 183, 184N, 185, 187, 277, 277A, 277B,2 78, 278A, 278B, 279, 279A, 280, 281, 282,283, 284, 287, 287B, 287C, 287D, 287E, 287J,310A,377,458A,477.
MME – Glue on Ceiling Tile area  MCB 1 X 1 Fissured
8,406 SF
Rooms and Spaces; 184B,258A, 277,278, 282,287, 287A, 287B, 287C, 287D, 287E, 287G, 287F, 287J, 281, 280A,280B.
This building is scheduled from demolition in July of 08, ACM will be removed in advance of demolition.

Pipe and Fitting in the ME Room was removed in June 04.